Production Schedule and weather forecast
Music Video Production Schedule (Mid-Dec to February)
Pre-Production Phase (Mid-December – Early January)
Week 1-2 (Mid-Dec to End-Dec)
Tasks:- Finalize the concept, storyboard, and shot list.
- Secure permits for locations.
- Hire cast, crew, and any needed specialists (e.g., choreographer, stunts).
- Scout and secure locations (consider weather and accessibility).
- Rent or purchase equipment.
- Schedule rehearsals, if needed.
Weather Considerations:
- Winter Conditions: If filming outdoors, weather may cause delays, so ensure locations have backup indoor options or covered spaces.
- Contingency Plans: Have an indoor shoot location ready if outdoor conditions (snow, rain, etc.) become problematic.
Week 3-4 (Early January)
Tasks:- Confirm all logistics (permits, insurance, transport, catering).
- Create a detailed shooting schedule for each day.
- Conduct costume fittings and rehearsals.
- Finalize equipment and transport logistics.
Weather Considerations:
- Cold Weather & Daylight: Days are shorter, so plan to work during daylight hours for outdoor shots. Factor in potential delays due to snow or ice.
- Contingency Plans: Pre-arrange backup indoor locations or studio time for certain shots.
Production Phase (Mid-January – February)
Week 5 (Mid-January)
Tasks:- Shoot the first segment of the music video (especially if it requires outdoor locations, so the weather is still manageable).
- Focus on scenes with a tighter timeline (e.g., ones requiring actors or complex stunts).
- Continue with rehearsals and prep.
Weather Considerations:
- Cold and Wet Conditions: Keep an eye on weather forecasts (snow, rain, etc.). Monitor the 7-day forecast closely and have backup plans.
- Contingency Plans: If temperatures drop dramatically or unexpected storms occur, move interior scenes up or shift to more controlled environments like soundstages.
Week 6-7 (Late January – Early February)
Tasks:- Film more difficult or riskier shots (e.g., stunts, water-based shots) during ideal weather conditions.
- Record any additional scenes that require specific weather elements (e.g., rain effects, snow).
- Continue shooting indoors as necessary.
Weather Considerations:
- Freezing Temps: Ice or snow may affect equipment or the crew's ability to work safely. Allow extra time for setup and weather-proofing equipment.
- Contingency Plans: In case of unexpected cold weather, schedule interior shooting (studio or warehouse). Consider lighting equipment for indoor shots.
Week 8 (Mid-February)
Tasks:- Wrap up any remaining outdoor shots.
- Focus on capturing any remaining visual effects or key performance shots.
- Final scenes, focusing on dynamic elements or extras.
- Begin editing footage as you shoot, if possible.
Weather Considerations:
- Variable Weather: Temperatures could fluctuate dramatically, so maintain flexibility with outdoor scenes.
- Contingency Plans: Ensure that any outdoor shooting is completed by early February in case the weather turns uncooperative.
Post-Production (Late February)
- Week 9 (End of February)
Tasks:- Finalize post-production (editing, VFX, color correction, etc.).
- Add any visual effects (snow, rain, etc.) if required.
- Finalize the music mix and sync with the visuals.
- Review and complete the final edit.
- Ensure all outdoor footage taken is usable by factoring in any weather issues that might have occurred during filming.
- Incorporate any weather-dependent effects (e.g., snowfall or sunshine).
- If weather made a shot unusable, discuss with the director/creative team about reshooting or digitally enhancing the final footage to correct the issue.
Contingency Planning
- Weather Forecast Monitoring: Always monitor forecasts 2-3 days in advance. Consider renting a weather app or working with a professional service that can predict weather disruptions.
- Indoor Backup Locations: Always have a secondary location to shoot indoors, especially if you’re depending on a large outdoor setup.
- Production Insurance: Ensure you have appropriate weather-related insurance to cover delays or damage.
Buffer Days
- Add 1-2 buffer days at the end of each month to handle unforeseen weather-related delays.
This schedule ensures we are prepared for winter conditions while maintaining a clear path toward completing the project on time.